PA: Contractor defaults on Findlay Connecter contract....construction at a pause

Construction on the southern two and a half miles of the Findlay Connector, which will connect US 22 to PA 60 and the Pittsburgh Airport, has ground to a halt recently. The reason, the contractor, Smith and Johnson, was declared in default by the PA Turnpike commission as a result of Smith and Johnson's financial woes. See article in today's Post-Gazette.

Smith and Johnson was awarded the contract to build Section 54C which runs from US 22 near Bavington to just north of Bald Knob Road. The contract included interchanges at US 22 and Bald Knob Road. According to the Post-Gazette article: Section 54C is 65 percent complete while Sections 54A and 54B are 77 and 76 percent complete, respectively. Most of the troubles began in the fall. And although a bridge carrying Candor Road over US 22 was demolished in late January, Smith and Johnson was pulling out from the construction site. On January 18, the Turnpike Commission offered the company a chance to right the ship, but those efforts failed and the Turnpike declared them in default on February 8.

Problems in addition to falling behind schedule include shortpaying or not paying at all their subcontractors and suppliers.

This would be the third major project in two states that Smith and Johnson has pulled out of. In September of 2005, Smith and Johnson halted work on a six mile segment of a 50 mile highway called the O'Bannon Expressway in Southern Indiana. Citing unanticipated $3,000 fuel costs and began a tussle with Indiana over who should pay for the additional costs.

According to this WISH-TV news story from September 15, 2005:

Indiana Department of Transportation officials said the contractor is bound by its contract to complete the job for the price it bid and that the state has no policy for allowing fuel-cost escalations. "This is very unusual. This hasn't happened anywhere else (in the state) this year," said department spokeswoman Afua Anokwa.

The company also stopped work on a US 231 project in Rockport, Indiana at the same time. The company laid of 30 employees.

It appears that this was a ploy to get INDOT's attention. Bob Johnson, general superintendent for S &J, said in a September 16, 2005 issue of Land Line Online that it was standard procedure for other partners to absorb part of the cost.

“There is sort of a standard they’ve used in other states,” he said. “The contractor absorbs the first 20 percent. Then after that, the governing agency or the contracting agency usually helps out with the fuel cost.”

The state ordered them back to work and they obliged.

However, according to today's article...it appears the company has gone out of business.

"As far as we know, they closed down the highway construction side of their business," Mr. Agnello said. "Basically, they're out of business."
As this develops, more will be reported here.




Comments

Popular posts from this blog

Interstate 40's Tumultuous Ride Through the Pigeon River Gorge

In the nearly 60 years Interstate 40 has been open to traffic through the Pigeon River Gorge in the mountains of Western North Carolina, it has been troubled by frequent rockslides and damaging flooding, which has seen the over 30-mile stretch through North Carolina and Tennessee closed for months at a time. Most recently, excessive rainfall from Hurricane Helene in September 2024 saw sections of Interstate 40 wash away into a raging Pigeon River. While the physical troubles of Interstate 40 are well known, how I-40 came to be through the area is a tale of its own. Interstate 40 West through Haywood County near mile marker 10. I-40's route through the Pigeon River Gorge dates to local political squabbles in the 1940s and a state highway law written in 1921. A small note appeared in the July 28, 1945, Asheville Times. It read that the North Carolina State Highway Commission had authorized a feasibility study of a "...water-level road down [the] Pigeon River to the Tennessee l...

Massena Center Suspension Bridge

The Massena Center Bridge, also known as the Holton D. Robinson Bridge, has had quite the tumultuous history. Situated on the Grasse River just east of Massena, New York in the hamlet of Massena Center, the Massena Center Bridge is a reminder of the efforts the community has made in order to connect over the river. The first and only other known bridge to be built at Massena Center was built in 1832, but that bridge was never long for this world. During the spring of 1833, the Grasse River dammed itself due to an ice dam, flooded and lifted the bridge off its foundation, destroying the bridge in the process.  The floods were frequent in the river during the spring, often backing up the river from Hogansburg and past Massena Center, but not to nearby Massena. After the first bridge disappeared, local residents had to resort to traveling seven miles west to Massena to cross the next closest bridge, and that was no easy task for a horse and buggy. However, it was many decades befo...

The Dead Man's Curve of Interstate 90 and Innerbelt Freeway in Cleveland

"Dead Man's Curve" refers to the transition ramp Interstate 90 takes between Cleveland Memorial Shoreway onto the Innerbelt Freeway in downtown Cleveland, Ohio.  Said curve includes a sharp transition between the two freeways which is known for a high rate of accidents.  Currently the curve (not officially named) has a 35 MPH advisory speed and numerous safety features intended to mitigate crashes.  When the Interstate System was first conceived during 1956, Interstate 90 was intended to use the entirety Cleveland Memorial Shoreway and connect to the Northwest Freeway through Lakewood.  The Innerbelt Freeway was initially planned as the northernmost segment of Interstate 71.  The extension of Cleveland Memorial Shoreway west of Edgewater Park was never constructed which led to Interstate 90 being routed through the Innerbelt Freeway.   Part 1; the history of Cleveland's Innerbelt Freeway and Deadman's Curve The Federal Aid Highway Act of 1956 was signe...