Skip to main content

The I-485 Blame Game

Yes, it's again time for the Interstate 485 blame game. And a recent article in the Charlotte Observer brings a whole litany of complaints, finger pointing, and disappointed drivers. So lets just list all of the complaints.

First, the section of I-485 from NC 16 to I-77 and NC 115 could end up opening two years behind its Spring 2007 original planned opening date.

So what went wrong? We've covered a few of them here at the blog.

The contractor Virginia Beach based Skanska lists their beefs:

First, when they were to begin surveying in December 2003. Not all of the land for the project had been owned by the State. The state counters with it is sometime common to have a few parcels of land not owned by the State at the start of construction. However, NCDOT does concede that the 14 parcels of land that in December 2003 were not purchased were a bit excessive.

Skanska claims that the lack of a completed right-of-way process forced them to access construction sites with more difficulty.

Other complaints from Skanska include the 62 extra days it took to move a major gas line along with five other utility relocation delays.

And finally the contractor contends that they did not receive plans to provide access to a Target and car dealership until the last minute and that the plans they received were hand drawn.

Skanska claims that the state has caused the project to be 311 days behind schedule, and has requested slightly over $8.5 million in additional compensation. The state, however, view the causes for the delays otherwise.

NCDOT feels that the contractor could have easily worked on other sections of the nearly six mile project while waiting for the utilities to be moved. They also do not believe that the company has not accurately computed their losses.

In addition, NCDOT points to a January 22nd letter that required Skanska to rebuild the asphalt base on the I-485/I-77 interchange ramps because it was too thin.

But the state does admit causing 138 days in delays.

Now onto the final segment of the loop. (I-77 to I-85 near Concord/University)

It still appears that the highway will not see any construction until 2015. It appears that a preliminary opening date is 2018. (Ten years from now). Considering the various funding, procedural, and construction delays, I'm willing to go out on a limb and say that it'll be 2021 before I-485 is officially done.

Now there is one ray of hope for completing I-485. Barry moose, who is the NCDOT engineer that oversees the Charlotte area, says that if the state can find the extra money to build the highway, construction could begin in 2011.

However, he didn't guarantee that if that would happen there would be no procedural or construction delays with it either.

Story: Charlotte Observer

Comments

Popular posts from this blog

Interstate 40's Tumultuous Ride Through the Pigeon River Gorge

In the nearly 60 years Interstate 40 has been open to traffic through the Pigeon River Gorge in the mountains of Western North Carolina, it has been troubled by frequent rockslides and damaging flooding, which has seen the over 30-mile stretch through North Carolina and Tennessee closed for months at a time. Most recently, excessive rainfall from Hurricane Helene in September 2024 saw sections of Interstate 40 wash away into a raging Pigeon River. While the physical troubles of Interstate 40 are well known, how I-40 came to be through the area is a tale of its own. Interstate 40 West through Haywood County near mile marker 10. I-40's route through the Pigeon River Gorge dates to local political squabbles in the 1940s and a state highway law written in 1921. A small note appeared in the July 28, 1945, Asheville Times. It read that the North Carolina State Highway Commission had authorized a feasibility study of a "...water-level road down [the] Pigeon River to the Tennessee l...

Massena Center Suspension Bridge

The Massena Center Bridge, also known as the Holton D. Robinson Bridge, has had quite the tumultuous history. Situated on the Grasse River just east of Massena, New York in the hamlet of Massena Center, the Massena Center Bridge is a reminder of the efforts the community has made in order to connect over the river. The first and only other known bridge to be built at Massena Center was built in 1832, but that bridge was never long for this world. During the spring of 1833, the Grasse River dammed itself due to an ice dam, flooded and lifted the bridge off its foundation, destroying the bridge in the process.  The floods were frequent in the river during the spring, often backing up the river from Hogansburg and past Massena Center, but not to nearby Massena. After the first bridge disappeared, local residents had to resort to traveling seven miles west to Massena to cross the next closest bridge, and that was no easy task for a horse and buggy. However, it was many decades befo...

The Dead Man's Curve of Interstate 90 and Innerbelt Freeway in Cleveland

"Dead Man's Curve" refers to the transition ramp Interstate 90 takes between Cleveland Memorial Shoreway onto the Innerbelt Freeway in downtown Cleveland, Ohio.  Said curve includes a sharp transition between the two freeways which is known for a high rate of accidents.  Currently the curve (not officially named) has a 35 MPH advisory speed and numerous safety features intended to mitigate crashes.  When the Interstate System was first conceived during 1956, Interstate 90 was intended to use the entirety Cleveland Memorial Shoreway and connect to the Northwest Freeway through Lakewood.  The Innerbelt Freeway was initially planned as the northernmost segment of Interstate 71.  The extension of Cleveland Memorial Shoreway west of Edgewater Park was never constructed which led to Interstate 90 being routed through the Innerbelt Freeway.   Part 1; the history of Cleveland's Innerbelt Freeway and Deadman's Curve The Federal Aid Highway Act of 1956 was signe...