Your May I-74/US 311 Freeway Progress Report

I took a drive Sunday to see what progress had been made in the last month on the I-74/US 311 Freeway from Business 85 in High Point to US 220 near Archdale. It had been a pretty dry month, but I didn't encounter as much progress on paving as I thought there should be. There were though many signs of progress. The post proceeds West to East (or Northwest to Southeast to be more accurate) along the nearly 10 miles of future freeway...
1. High Point East Belt, Business 85 to I-85 High Point
A. Baker Road-They have almost completed removing the old road bed and cutting down to the grade of the surrounding roadway...
Here's what remains of the westbound temporary road. Looking into the roadbed...
There are some rock and soil to remove to bring it down to grade. Looking east/south from the bridge, one can see there has been more progress on grading since April...
But there still needs more work to be done looking back west/north toward the completed road and High Point...
B. Jackson Lake Road-The final layer of asphalt had been put down on the bridge and its approaches in late April:
Some progress had been made in grading and landscaping the westbound lanes to the north/west of the bridge...
The view to the south and east is mostly similar to last month's, with the exception of more landscape vegetation...
C. Kersey Valley Road-The next stop was at the bridge in the distance along Kersey Valley Road. Like with Jackson Lake, the final asphalt layer had been placed on and near the bridge...
The following is a reverse view of the last Jackson Lake photo, looking toward that road's bridge from Kersey Valley...
One gets more of a sense of a near completed freeway from this vantage point, however looking the other way shows that there's more to do:
They are working on some more environmentally friendly run-off structures, like here...
This photo is taken from Dresden Road. Note the rock runoff stream paths and the small containment pond below. An overflow pipe is included to prevent runover from the pond in the background.

D. I-85 Bridges and Ramps-A close look at the bridges and Eastbound off ramp shows orange barrels blocking the ramp. This could mean the ramps and bridges are completed and construction trucks need to exit on a new link to the road seen to the right in front of the barrels...
Through traffic was put back on the original I-85 lanes in mid-April. While there are only two of the 3 lanes available southbound all 3 are open northbound. Traveling south on I-85, the first advanced exit sign is 2 miles away from the exit and covered over...
Though not visible, from the plans the sign should read Exit 133C, B, A I-74/US 311/NC 62 High Point, Asheboro, There's another covered over sign at 1 mile, the signs where the C/D ramps begin had not been put up, but one sign assembly at the future I-74 Westbound ramp has...
Traffic needing to access NC 62 now uses the C/D ramps. But one cannot get back on I-85 for now since the end of the ramps are blocked by Jersey Barriers...
This is a better view of the Exit 113A sign than that was shown in the March posting.
Going northbound at I-85 there is an advance sign at 1 mile covered over, and a sign at the beginning of the C/D ramps They still need to be place though before the separate NC 62 exit...

2. "US 311 Bypass" I-85 to US 220 Randleman
A. Tuttle Road-Nothing new was seen at Tuttle Road, the final coat of asphalt had been placed along the bridge in early April, and the road bed was already landscaped with guard rails installed.

B. Poole Road-On the north/ westbound side of the bridge new asphalt had been placed around the completed creek bridge...
The view south/ eastbound showed more work had been completed on landscaping...
Many of the water runoff drains had been completed, here's a closeup of one from Poole Road halfway toward the Cedar Square Interchange...
C. Cedar Square Road and Interchange-Not as much had been accomplished here as hoped. Though much of the unfinished roadway does not have to be completed until the next segment to US 220 is completed in 2012-
Certainly a lot of construction vehicles available to do the work. To the center middle is the eastbound off ramp to Cedar Square Road which will also temporarily be US 311.
The grading progress under the bridge depends when each roadbed is suppose to open, to the left this year, to the right in two years...
Landscaping is complete, in fact the grass could be mowed. Here's a view of the progress on the Westbound onramp and future eastbound offramp at the intersection of Poole and Cedar Square:
The on ramp curves off to the right, a better view of it and the surrounding landscaping can be seen here...
Looks like between the ramps and the eastbound lanes will be another runoff containment area.

D. 'US 311' Interchange-Much more progress in clearing and moving of dirt can be seen this month. Here's approaching the future interchange along South US 311...
The clearing continues across the road to the south through the gap in the trees in front of the radio towers and to the southeast, I assume toward US 220. Below is a closer look at the interchange area showing the dirt that has been moved to create the future highway roadbed. There are two roads (one with the machinery on it, the other between that and the current roadway), whether this means the route will be divided at this point, or one of the beds is for a ramp is not quite clear:
E. US 220 Interchange-More progress can be seen in building the sides of the future westbound I-74 bridge. Here's what the construction area looks like approaching on 220 south...
The future I-74 East will use the first bridge support, westbound traffic heading north on 220 (I-73 North) will use the bridge in the background. Here's a closer look at that bridge:
On the left you can see the start of building the other side of the bridge, which is better seen here...
The ramp behind leads to the flyover ramp for I-74 west traffic. Here's a view of the construction area from US 220 North:
A closer look at the bridge construction seen in the distance above...
You can see to the left clearing behind the bridge which may lead all the way back to US 311. While not as much progress as I would have thought occurred (the amount of progress for April has not yet been posted by NCDOT), it still looks possible for this road to open this summer and not late in the year as NCDOT schedule currently states.

Comments

Anonymous said…
Obviously the new stretch of highway is going to be name I-74. Is any of the existing US 311 going to be renamed? Say the stretch between Bus 85 and Main St in High Point where the majority of the road is already interstate standard?

Popular posts from this blog

Old US Route 60/70 through Hell (Chuckwall Valley Road and Ragsdale Road)

Back in 2016 I explored some of the derelict roadways of the Sonoran Desert of Riverside County which were part of US Route 60/70; Chuckwalla Valley Road and Ragsdale Road. US 60 and US 70 were not part of the original run of US Routes in California.  According to USends.com US 60 was extended into California by 1932.  US 60 doesn't appear on the California State Highway Map until the 1934 edition. USends.com on US 60 endpoints 1934 State Highway Map Conversely US 70 was extended into California by 1934, it first appears on the 1936 State Highway Map. USends.com on US 70 endpoints 1936 State Highway Map When US 60 and US 70 were extended into California they both utilized what was Legislative Route Number 64 from the Arizona State Line west to Coachella Valley.  LRN 64 was part of the 1919 Third State Highway Bond Act routes.  The original definition of LRN 64 routed between Mecca in Blythe and wasn't extended to the Arizona State Line until 1931 acc...

Trimmer Springs Road (Fresno County)

Trimmer Springs Road is an approximately forty-mile rural highway located in Fresno County.  The corridor begins near in California State Route 180 in Centerville and extends to Blackrock Road at the Kings River in the Sierra Nevada range near the Pacific Gas & Electric Company town of Balch Camp. The roadway is named after the former Trimmer Springs Resort and was originally constructed to facilitate access to the Sanger Log Flume.  Trimmer Springs Road was heavily modified and elongated after construction of Pine Flat Dam broke ground in 1947.   Part 1; the history of Trimmer Springs Road Much of the original alignment of Trimmer Springs Road was constructed to facilitate access to the Sanger Log Flume.   The  Kings River Lumber Company  had been established in 1888 in the form of a 30,000-acre purchase of forest lands in Converse Basin.  This purchase lied immediately west of Grant Grove and came to be known as "Millwood."  The co...

When was Ventura Avenue east of downtown Fresno renamed to Kings Canyon Road? (California State Route 180)

California State Route 180 was one of the original Sign State Routes designated in August 1934.  The highway east of Fresno originally utilized what was Ventura Avenue and Dunlap Road to reach what was then General Grant National Park.  By late year 1939 the highway was extended through the Kings River Canyon to Cedar Grove.   In 1940 General Grant National Park would be expanded and rebranded as Kings Canyon National Park.  The Kings Canyon Road designation first appeared in publications circa 1941 when the California State Route 180 bypass of Dunlap was completed.  Kings Canyon Road ultimately would replace the designation of Dunlap Road from Dunlap to Centerville and Ventura Avenue west to 1st Street in Fresno.   The Kings Canyon Road would remain largely intact until March 2023 when the Fresno Council designated Cesar Chavez Boulevard.  Cesar Chavez Boulevard was designated over a ten-mile corridor over what was Kings Canyon Road, remaini...