The northwest quadrant of Interstate 485 has had a laundry list of issues. Concrete and asphalt problems, sign problems, and other delays has caused portions of the highways to fall 18 months behind schedule. Well, if all goes well this week (And with I-485's history, it won't.), an additional 2.3 miles of Interstate 485 will open to traffic. See today's Charlotte Observer for more. The new opening will be from Interstate 85 in western Mecklenburg County northwards to NC 27 (Mount Holly Road). There is also an exit with Moores Chapel Road in between. This is the first of three segments of Interstate 485 to open between now and the first half of 2007. Early in 2007, the highway is to open a few miles further north from NC 27 to Brookshire Blvd. (NC 16). Then later in 2007, the Northwest corner will be complete as I-485 will be extended further to Interstate 77 and NC 115 near Huntersville. It is believed that this part of I-485 will ease traffic on NC 16 and NC 27 fr...
Because every road has a story.