Skip to main content

Perdue offers I-485 financing plan, but many questions need to be answered first

Earlier today, Governor Perdue announced her plan to complete the Interstate 485 loop in the next five years. The plan is something called a design-build-finance plan, and it has yet to be used within North Carolina. However, there are a number of hurdles and loopholes within the plan

The term 'design-build' is familiar within North Carolina transportation projects. Design-build projects are where the builder also designs the overall project- often while the project is ongoing. One of North Carolina's first design-build projects was the Interstate 85 widening between miles 40-48.

'Design-build-finance' is where the contractor pays for some or all of the construction and then gets reimbursed by the state within a specified period of time. This method has been used elsewhere in the country including an Interstate 69 reconstruction project in Michigan.

The projected cost to complete the remaining five miles of I-485 is now roughly $340 million.

Under this plan, construction for I-485 will start next year and be completed by 2015. Plus, the governor's office emphasizes that money will not come from or delay other projects.

Sounds too good to be true right? The contractor pays for some of the construction, gets paid back by the state, no other projects get delayed.

Well, I need that Lee Corso photo again...because "Not so fast, my friend!"

First, the financing method. The contractor would pay $50 million of the $340 million to construct the highway. Well, first you have to find a construction firm that has $50 million in cash to finance the highway. And with troubles NCDOT has had with various construction companies over the past decade, that's not a guarantee.

Adam Froehlig, in a post to a national transportation forum, notes that this approach was tried for Minnesota's Crosstown Commons project but no construction firm placed a bid.

The $50 million that the construction company puts down for the highway would be paid back by the state over a 10 year period. Questions come from that too. What will the interest rate be...will the money owed to the construction company, somewhere between $5-6 million a year, impact financing other projects? With the state and the DOT in the red, will the state be able to pay it back over that period?

If the contractor is only paying $50 million or 14.7% of the costs, where is the other money coming from? The Governor's office says that no other project will be delayed. Well, according to the Charlotte Observer, the DOT's chief financial officer, Mark L. Foster, admits that the DOT is 'prioritizing' projects statewide, including I-485. If this is the case, then aren't other projects going to be delayed? Plus, when the missing five miles cost only $220 to construct - the state said they had no money to complete it. Now, they need to come up with $290 million - that's $70 million more than the original estimated cost - and suddenly NCDOT has the money.

The highway that most likely will be delayed is Interstate 295 in Fayetteville, which has the whipping boy for every other city in the state who has seen delays in their planned freeway loops.

Personally, I'd like to see where this $290 million will come from. Will the controversial equity formula be repealed? Will they try to sneak in tolls? Something just doesn't add up here.

There are other hurdles for the highway - specifically environmental concerns. Charlotte has had a growing ozone (ground level) issue and has been under the careful eye of the US Environmental Protection Agency. In fact, highway funding for Charlotte has been threatened to be cutoff if the metro area didn't improve air quality. Groups like the Southern Environmental Law Center will be certain to keep a close eye on this process.

Now what if this works?

Well, as the economy improves, more construction companies will be able to assist in financing similar projects. This could possibly speed up delayed projects and also eliminate future projects becoming toll roads.

So there could be a new opportunity for the future of North Carolina highways. However, this is a big test, and a lot of interested parties will be keeping their eye on how the final five miles of Interstate 485 eventually gets built. There is a lot riding on this project - not only politically for Governor Perdue - but on how other highway projects in North Carolina are built short and long term. It will be an interesting few months and years to see how this all unfolds.

Story Links:
I-485 plan: Tap builder cash ---Charlotte Observer
Gov. says work to finish I-485 will start in 2010 ---WBTV-TV
Governor says I-485 will be completed in five years ---WCNC-TV
Perdue unveils plan to complete Interstate 485 ---News14Carolina

Comments

This comment has been removed by a blog administrator.
Anonymous said…
This comment has been removed by a blog administrator.

Popular posts from this blog

Interstate 40's Tumultuous Ride Through the Pigeon River Gorge

In the nearly 60 years Interstate 40 has been open to traffic through the Pigeon River Gorge in the mountains of Western North Carolina, it has been troubled by frequent rockslides and damaging flooding, which has seen the over 30-mile stretch through North Carolina and Tennessee closed for months at a time. Most recently, excessive rainfall from Hurricane Helene in September 2024 saw sections of Interstate 40 wash away into a raging Pigeon River. While the physical troubles of Interstate 40 are well known, how I-40 came to be through the area is a tale of its own. Interstate 40 West through Haywood County near mile marker 10. I-40's route through the Pigeon River Gorge dates to local political squabbles in the 1940s and a state highway law written in 1921. A small note appeared in the July 28, 1945, Asheville Times. It read that the North Carolina State Highway Commission had authorized a feasibility study of a "...water-level road down [the] Pigeon River to the Tennessee l...

Massena Center Suspension Bridge

The Massena Center Bridge, also known as the Holton D. Robinson Bridge, has had quite the tumultuous history. Situated on the Grasse River just east of Massena, New York in the hamlet of Massena Center, the Massena Center Bridge is a reminder of the efforts the community has made in order to connect over the river. The first and only other known bridge to be built at Massena Center was built in 1832, but that bridge was never long for this world. During the spring of 1833, the Grasse River dammed itself due to an ice dam, flooded and lifted the bridge off its foundation, destroying the bridge in the process.  The floods were frequent in the river during the spring, often backing up the river from Hogansburg and past Massena Center, but not to nearby Massena. After the first bridge disappeared, local residents had to resort to traveling seven miles west to Massena to cross the next closest bridge, and that was no easy task for a horse and buggy. However, it was many decades befo...

The Dead Man's Curve of Interstate 90 and Innerbelt Freeway in Cleveland

"Dead Man's Curve" refers to the transition ramp Interstate 90 takes between Cleveland Memorial Shoreway onto the Innerbelt Freeway in downtown Cleveland, Ohio.  Said curve includes a sharp transition between the two freeways which is known for a high rate of accidents.  Currently the curve (not officially named) has a 35 MPH advisory speed and numerous safety features intended to mitigate crashes.  When the Interstate System was first conceived during 1956, Interstate 90 was intended to use the entirety Cleveland Memorial Shoreway and connect to the Northwest Freeway through Lakewood.  The Innerbelt Freeway was initially planned as the northernmost segment of Interstate 71.  The extension of Cleveland Memorial Shoreway west of Edgewater Park was never constructed which led to Interstate 90 being routed through the Innerbelt Freeway.   Part 1; the history of Cleveland's Innerbelt Freeway and Deadman's Curve The Federal Aid Highway Act of 1956 was signe...