The Gateway Bridge of Taylor, Michigan (Interstate 94 and US Route 24)


The Gateway Bridge is an overpass structure which separates Interstate 94 and US Route 24 (Telegraph Road) in Taylor, Michigan. This span is a unique tied arch design which was completed during Fall 2005 in advance of Super Bowl XL. The bridge is intended to serve as the "gateway to Detroit" for travelers heading east on Interstate 94 into the city.




The Gateway Bridge of Taylor, Michigan

The Gateway Bridge was a replacement for the original overpass bridges separating Interstate 94 and US Route 24 (Telegraph Road) in Taylor.  The structure was developed by the Detroit Regional Gateway Advisory as project slated to be completed in advance of Super Bowl XL.  The span was intended to serve as a figurative gateway to the urban core of Detroit for travelers heading east from Metro Airport on Interstate 94. 

Construction of the Gateway Bridge began during May 2004 during which Interstate 94 continued to use the original overpass bridges crossing US Route 24.  The span was completed during Fall 2005 and was part of a wider improvement corridor consisting of eighteen miles of improvements to Interstate 94.  

The tied arch design of the Gateway Bridge is readily apparent for travelers on Interstate 94.  


The full span of the Gateway Bridge is best observed from US Route 24.  The structure is 250 feet long and is painted in a distinctive blue color which contrasts from most normal freeway overpasses. 

Comments

Popular posts from this blog

Bleriot Ferry - Alberta

  Alberta operates six ferries scattered throughout the province. Roughly twenty to twenty-five kilometers up the Red Deer River from the town of Drumheller is one of the most scenic ferry crossings in all of Wild Rose Country, the Bleriot Ferry. Using the North Dinosaur Trail (Alberta Highway 838, or AB 838), the Bleriot Ferry provides a scenic river cruise of sorts in the Canadian Badlands. The Bleriot Ferry started operating in 1913 as the Munson Ferry when a few bridges crossed the Red Deer River. The ferry was started by Andre Bleriot, the brother of famed early aviator Louis Bleriot, who became famous for being the first person to fly over the English Channel. At the time, the Alberta provincial government commissioned local residents to run the ferries. There were several ferries along the Red Deer River, and not only did they serve as vital transportation links, but they also served as local social hubs, since everyone had to take the ferries to go places. Over time, as the...

The Pollasky Bridge

The Pollasky Bridge near modern day Friant is a ruined highway bridge which was completed during early 1906 as part of the Fresno-Fresno Flats Road.  The structure is one of the oldest known arch concrete spans to have been constructed in California.  The bridge briefly carried California State Route 41 following the destruction of the Lanes Bridge in 1940.  The Pollasky Bridge itself was destroyed by flooding during 1951, but the ruins can still be found on the Madera County side of the San Joaquin River.   Pictured as the blog cover is the Pollasky Bridge as it was featured in the 1913 book "The Concrete Bridge."  The structure can be seen crossing the San Joaquin River near Friant below on the 1922 United States Geological Survey Map.   Part 1; the history of the Pollasky Bridge The Pollasky Bridge site is near modern day Friant of Fresno County.  The community of Friant was established as Converse Ferry during 1852 on the San Joaquin Rive...

I-73/I-74 and NC Future Interstates Year in Review 2024

Welcome to another annual review of progress in constructing North Carolina's New and Future Interstate routes. While 2024 was not too exciting, with no new segments of major routes opening, there was 1 new interstate signing, another proposed new interstate route, and the near opening of a new segment for 2 routes. As tradition, I will start off with a review of what happened with I-73 and I-74 and then move on to the major news of the year about the other new and future routes. Work continued on the I-73/I-74 Rockingham Bypass through the year. The last few months have been hoping for news of its opening before 2025, without luck. Signs of its near completion included the placement of new signs, many with interstate shields uncovered, along the Bypass and intersecting roadways. For example, these went up along US 74 East: Overhead signage at Business 74 exit which contains the future ramp to I-73 North/I-74 West. Signage was also updated heading west on US 74 approaching the unop...