The flex lanes of US Route 23 between Ann Arbor and Brighton


The flex lane corridor of US Route 23 in Michigan exists on the freeway segment between Ann Arbor and Brighton.  The flex lanes serve as an experimental temporary third lane only during commute hours.  The lanes are intended to mitigate the numerous safety issues the freeway segment is associated with.  The initial flex lanes opened between Ann Arbor and Whitmore Lake in 2017.  Construction broke ground on a corridor extension north to Brighton in 2023.



Part 1; the history of the US Route 23 flex lanes between Ann Arbor and Brighton

The US Route 23 freeway corridor between Ann Arbor and Whitmore Lake was completed during 1957.  The corridor was expanded north to Interstate 96 in Brighton by 1960.  Despite being over sixty years old the freeway between Ann Arbor and Brighton has seen little expansion but has had an increasing number of commuters use it.  This has led to safety and congestion issues which have been only worsening with time.  

During November 2016 a $92,000,000 improvement project between Ann Arbor and Whitmore Lake began.  The improvements consisted of reconstructing the antiquated freeway ramps and adding part-time interior shoulder flex lanes.   The project zone was completed, and the flex lanes made functional during November 2017.  The flex lanes were opened to commuter traffic during the hours of 6 AM-9 AM and 4 PM-7 PM Monday-Friday.

An extension of the US Route 23 flex lanes north of M-36 in Whitmore Lake to Interstate 96 in Brighton was announced during July 2020.  The flex lane extension north to Interstate 96 was priced an estimated $150,000,000 and also include the reconstruction of numerous antiquated freeway ramps.  The corridor would break ground during 2023 and is ongoing as of the publishing of this blog.  



Part 2; scenes along the flex lanes of US Route 23 between Ann Arbor and Whitmore Lake

Below northbound US Route 23 can be seen approaching Site 46N in the Ann Arbor-Whitmore Lake flex lane corridor.  Site 46N denotes a crash investigation site at Mile Marker 46 north of Warren Road.  Motorists can use these crash sites to pull off the travel lanes of US Route 23 after minor accidents.  


Below an overhead Variable Message Sign announces the current status of the flex lanes.  Overhead gantries also display the lane status along with variable speed limits for the general use lanes based on the traffic conditions.


The US Route 23 connector ramp to M-36 is currently closed so it can be reconstructed.  


US Route 23 north of M-36 can be seen split partially to the grade of the southbound lanes to aid in the flex lane expansion to Interstate 96.


Comments

Popular posts from this blog

Bleriot Ferry - Alberta

  Alberta operates six ferries scattered throughout the province. Roughly twenty to twenty-five kilometers up the Red Deer River from the town of Drumheller is one of the most scenic ferry crossings in all of Wild Rose Country, the Bleriot Ferry. Using the North Dinosaur Trail (Alberta Highway 838, or AB 838), the Bleriot Ferry provides a scenic river cruise of sorts in the Canadian Badlands. The Bleriot Ferry started operating in 1913 as the Munson Ferry when a few bridges crossed the Red Deer River. The ferry was started by Andre Bleriot, the brother of famed early aviator Louis Bleriot, who became famous for being the first person to fly over the English Channel. At the time, the Alberta provincial government commissioned local residents to run the ferries. There were several ferries along the Red Deer River, and not only did they serve as vital transportation links, but they also served as local social hubs, since everyone had to take the ferries to go places. Over time, as the...

The Pollasky Bridge

The Pollasky Bridge near modern day Friant is a ruined highway bridge which was completed during early 1906 as part of the Fresno-Fresno Flats Road.  The structure is one of the oldest known arch concrete spans to have been constructed in California.  The bridge briefly carried California State Route 41 following the destruction of the Lanes Bridge in 1940.  The Pollasky Bridge itself was destroyed by flooding during 1951, but the ruins can still be found on the Madera County side of the San Joaquin River.   Pictured as the blog cover is the Pollasky Bridge as it was featured in the 1913 book "The Concrete Bridge."  The structure can be seen crossing the San Joaquin River near Friant below on the 1922 United States Geological Survey Map.   Part 1; the history of the Pollasky Bridge The Pollasky Bridge site is near modern day Friant of Fresno County.  The community of Friant was established as Converse Ferry during 1852 on the San Joaquin Rive...

I-73/I-74 and NC Future Interstates Year in Review 2024

Welcome to another annual review of progress in constructing North Carolina's New and Future Interstate routes. While 2024 was not too exciting, with no new segments of major routes opening, there was 1 new interstate signing, another proposed new interstate route, and the near opening of a new segment for 2 routes. As tradition, I will start off with a review of what happened with I-73 and I-74 and then move on to the major news of the year about the other new and future routes. Work continued on the I-73/I-74 Rockingham Bypass through the year. The last few months have been hoping for news of its opening before 2025, without luck. Signs of its near completion included the placement of new signs, many with interstate shields uncovered, along the Bypass and intersecting roadways. For example, these went up along US 74 East: Overhead signage at Business 74 exit which contains the future ramp to I-73 North/I-74 West. Signage was also updated heading west on US 74 approaching the unop...